Home · week of 14–18 September 2026
This week
Phase 1 closed on paper 31 August 2026 and four closeouts are still open, so they read Late. Phase 2 work starts now. A task can only be marked Done once its workpaper has a file location recorded in the register.
Late closeouts
4 of 4
Start this week
4 of 4
Base-year progress
Phase 2 · 10%
Workpapers locked
1 of 22
Late — Phase 1 closeouts
Due 31 Aug 2026
- Late
L1 Close plan + calendar
Charlotte Gallant · Phase 1 ended 31 Aug 2026
Workpaper: FY27 base-year plan & calendar · file location on record
- Late
L2 Close FY18 / consultant watchlist
OSP F&A Rate Team · Phase 1 ended 31 Aug 2026
Workpaper: FY18 consultant watchlist closeout memo · needs a file location before it can close
- Late
L3 Close source-data inventory
Monica Patel · Phase 1 ended 31 Aug 2026
Workpaper: Source-data inventory · file location on record
- Late
L4 Confirm no system/reorg extension needed
Charlotte Gallant · Phase 1 ended 31 Aug 2026
Workpaper: System / reorg extension assessment · needs a file location before it can close
Start this week — Phase 2
14–18 Sep 2026
- This week
W1 Clone prior CRIS model into FY27 base-year model
Monica Patel · Week of 14–18 Sep 2026
Workpaper: FY27 CRIS model shell (cloned) · needs a file location before it can close
- This week
W2 Open staging and first CoA / dept / payroll pull
Monica Patel · Week of 14–18 Sep 2026 · Pull range 7/1/26 – 12/31/26
Workpaper: Staging load log — CoA / dept / payroll · needs a file location before it can close
- This week
W3 Name rollup owners
Monica Patel · Thu 17 Sep standup
Workpaper: Rollup owner assignment sheet · needs a file location before it can close
- This week
W4 Send Maureen space-file request
Thanh Tran · Fri 18 Sep · Space file target 31 Oct 2026
Workpaper: Maureen space-file request & response · needs a file location before it can close
Hard dates
- Base year FY271 Jul 2026 – 30 Jun 2027This week
- Phase 1 close31 Aug 2026 — still openLate
- Maureen space file — Thanh Tran31 Oct 2026Upcoming
- 6-month CRIS model — Monica Patel28 Feb 2027Upcoming
- Locked model + negotiation package18 Dec 2027Upcoming
- 90-day CAS extension yes/no — OSP Leadership18 Dec 2027Upcoming
Timeline
Nine phases, May 2026 – December 2027
Phase end dates are Charlotte Gallant's to change. Percentages reflect the current build state: Phase 1 complete, Phase 2 just underway.
Gantt · May 2026 – Dec 2027
Marker = week of 14 Sep 2026
Phase 1
Planning & prior-year review
1 Jul – 31 Aug 2026
Scope the FY27 base year, review the three standing rate agreements as context, close the FY18 consultant watchlist and the source-data inventory.
Owner · Charlotte Gallant
Phase 2
Configure CRIS & load Q1–Q2
1 Sep 2026 – 28 Feb 2027
Clone the prior model, stand up staging, load CoA / dept / payroll for the first two quarters. 6-month CRIS model due 28 Feb 2027.
Owner · Monica Patel
Phase 3
Financial & compliance scrubs
1 Oct 2026 – 30 Apr 2027
Unallowables, exclusions, transfers. Clean-data narrative due 30 Jun 2027.
Owner · Cost Analyst
Phase 4
Space by function (ASF)
through 31 Oct 2027
Functional-use survey and ASF assignment by rate area; Maureen space file feeds this.
Owner · Thanh Tran
Phase 5
Central services allocations
1 Mar – 30 Sep 2027
Step-down of central service centers to benefiting functions, with documented bases.
Owner · Charlotte Gallant (sign-off)
Phase 6
Admin pools by rate area
1 Apr – 31 Jul 2027
General, departmental and sponsored-projects administration pools per rate area.
Owner · Cost Analyst + HMS F&A
Phase 7
Final FY27 load & recon
1 Jul – 15 Oct 2027
Full-year load, tie-out to the audited statements, variance explanations.
Owner · Monica Patel + Cost Analyst
Phase 8
Interest, depreciation, facilities, library
1 Sep – 15 Oct 2027
Building and equipment depreciation, interest, O&M and library cost components.
Owner · Monica / Thanh / OSP F&A
Phase 9
Review, lock, extension call
1 Oct – 18 Dec 2027
Internal review, model lock, negotiation package to DHHS Cost Allocation Services, 90-day CAS extension decision.
Owner · Charlotte Gallant + OSP Leadership
Team
Five seats
Each seat has a boundary. Work outside the boundary goes back to the owning seat rather than being absorbed.
Scope & lock
Charlotte Gallant
Does
- +Sets and changes phase end dates
- +Signs off central services allocations
- +Declares the model locked
Does not
- —Build CRIS loads
- —Decide the 90-day CAS extension
- —Assign space by function
CRIS model
Monica Patel
Does
- +Clones and configures the FY27 base-year model
- +Runs CoA / dept / payroll pulls and rollups
- +Delivers the 6-month model 28 Feb 2027
Does not
- —Change phase end dates
- —Approve allocation policy
- —Negotiate with DHHS
Space
Thanh Tran
Does
- +Owns the Maureen space-file request (31 Oct 2026)
- +Functional-use survey and ASF by rate area
- +Facilities inputs for Phase 8
Does not
- —Touch payroll data
- —Set pool structures
- —Lock the model
Scrubs & pools
Cost Analyst
Does
- +Financial and compliance scrubs
- +Builds admin pools by rate area
- +Full-year reconciliation with Monica
Does not
- —Own the calendar
- —Sign off allocations
- —Answer DHHS directly
Policy & negotiation
OSP F&A Rate Team
Does
- +Closes the FY18 / consultant watchlist
- +Owns treatment policy questions
- +Carries the negotiation package to Cost Allocation Services
Does not
- —Edit the CRIS model
- —Change phase end dates
- —Collect space data
Documents register
Workpapers by phase
Set a status and record where the file actually lives. The file location is what makes a task closable.
P1 Planning & prior-year review
1 Jul – 31 Aug 2026
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D01 FY27 base-year plan & calendar | Charlotte Gallant | ||
| D02 Prior-year rate agreement summary (3 areas) | OSP F&A Rate Team | ||
| D03 FY18 consultant watchlist closeout memo | OSP F&A Rate Team | ||
| D04 Source-data inventory | Monica Patel | ||
| D05 System / reorg extension assessment | Charlotte Gallant |
P2 Configure CRIS & load Q1–Q2
1 Sep 2026 – 28 Feb 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D06 FY27 CRIS model shell (cloned) | Monica Patel | ||
| D07 Staging load log — CoA / dept / payroll | Monica Patel | ||
| D08 Rollup owner assignment sheet | Monica Patel | ||
| D09 6-month CRIS model (28 Feb 2027) | Monica Patel |
P3 Financial & compliance scrubs
1 Oct 2026 – 30 Apr 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D10 Unallowable cost scrub workpaper | Cost Analyst | ||
| D11 Exclusions & transfers reconciliation | Cost Analyst | ||
| D12 Clean-data narrative (30 Jun 2027) | Cost Analyst |
P4 Space by function (ASF)
through 31 Oct 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D13 Maureen space-file request & response | Thanh Tran | ||
| D14 Functional-use survey results | Thanh Tran | ||
| D15 ASF by function and rate area | Thanh Tran |
P5 Central services allocations
1 Mar – 30 Sep 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D16 Central service center step-down workpaper | Charlotte Gallant |
P6 Admin pools by rate area
1 Apr – 31 Jul 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D17 Admin pool build — University Area | Cost Analyst | ||
| D18 Admin pool build — HMS / Chan SPH | HMS F&A |
P7 Final FY27 load & recon
1 Jul – 15 Oct 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D19 Full-year FY27 load & tie-out | Monica Patel |
P8 Interest, depreciation, facilities, library
1 Sep – 15 Oct 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D20 Interest, depreciation & library components | Monica Patel |
P9 Review, lock, extension call
1 Oct – 18 Dec 2027
| Workpaper | Owner | Status | File location |
|---|---|---|---|
| D21 Locked model + negotiation package | Charlotte Gallant | ||
| D22 90-day CAS extension decision memo | OSP Leadership |
Rules
How this build stays honest
Three standing rules. They are not preferences; they decide who may move what.
01
Only Charlotte changes phase end dates
Anyone may flag slippage. The calendar itself moves only through Charlotte Gallant, so the nine-phase window stays a single source of truth.
02
Only OSP Leadership decides the 90-day CAS extension
The yes/no is due 18 Dec 2027 alongside the locked model. No team member may assume the extension while planning work.
03
A task is done only when its document has a file location
Status alone is not completion. Until the workpaper's file location is recorded in the register, the task stays open on this week's board.
Scope note
This is the institutional FY27 indirect-cost base-year build supporting a federal F&A rate proposal to DHHS Cost Allocation Services. The three existing rate agreements — University Area, HMS and Chan SPH — are context for the new proposal, not deliverables of it.
Links
External references